VA Pamphlet 26-7 Chapter 14, Topic 2: Inspection Stages

Document
VA Lender's Handbook, VA Pamphlet 26-7
Version in Zeitro Strata
Where
pages 339–344 of 461

Page 339

Topic 2. Inspection Stages

July 14, 2003

Introduction

This topic contains information about

displaying legal notices

the stages of inspection

what inspectors look for during the inspection

re-inspections

special inspections, and

missed inspections.

Equal Employment Opportunity Poster Requirement

At the initial inspection, inspectors will note any failure of the builder to prominently display VA Poster 26-83-1, Equal Employment Opportunity is the Law, as a noncompliance item on the inspection report. Each contractor and subcontractor must display the poster in conspicuous places at job sites covered by VA value notices for proposed construction.

In all areas with significant concentrations of Spanish-speaking people, VA Poster 26-83-1(S) printed in Spanish, must be displayed next to the poster in English.

Page 340

When noncompliance with the poster requirement is found, the VA office of jurisdiction will immediately inform the builder that no further inspections will be made until the poster is displayed.

Obtaining Equal Employment Opportunity Posters

VA supplies the poster to the builder with the VA value notice, if issued by the VA. Although one poster may be used to cover a group of properties being constructed simultaneously by a builder, VA will furnish additional posters needed for adequate coverage.

Posters are available from the VA Forms and Publications Depot.

First Inspection Stage Alternatives

VA will notify builders, lenders, and inspectors which of the following first stage inspection alternatives are to be used in specific areas:

Excavation complete and ready for footings and foundations usually applies in localities where it is advisable to have the bearing soil examined before construction proceeds, or

Foundation walls complete and ready for backfill usually applies where soil conditions are generally uniform and free of faults likely to cause foundation problems.

Completion of Excavation Alternative

For the completion of excavation alternative, VA inspects

display of VA Poster 26-83-1, Equal Employment Opportunity is the Law

the nature of the bearing soil

form work for footings or the condition and quality of the footing trench if forms are not required, and

compliance with construction exhibits and VA Minimum Property Requirements regarding

- the location of the structures on the plot, and

- depth of excavation and its relation to street and proposed finish grades and to grades of adjoining improved properties.

Completion of Foundation Alternative

For the completion of foundation alternative, all of the above items will be observed and reported. In addition, VA will inspect

the size, location, and condition of all footings, foundation walls, piers, and other supporting members, and

the quality of materials and workmanship of masonry, damp proofing, and foundation drainage.

Second Inspection Stage

During the second inspection stage VA inspects

Page 341

all construction below the superstructure not installed or which was installed but not inspected or reported upon at the first inspection stage, including footings, foundations, piers, columns, waterproofing and drainage provisions

construction of the superstructure, including quality of materials and workmanship, details of construction, and the suitability of arrangement of all items for subsequent installation of equipment and of interior and exterior finishing materials

plan of the dwelling, including the arrangement of partitions and the sizes and placement of all openings

roughing-in of mechanical work, including plumbing, heating, and electric installations with respect to

- providing for the correct installation of fixtures, equipment, and accessories

- avoiding impairment of the strength of structural members, and

- proper operation of the completed systems.

Note: No second stage inspection of the dwelling is required for modular construction since the unit is fabricated in a factory and must be inspected to state standards.

Third Inspection Stage

During the third inspection stage VA inspects for acceptable completion of all specified onsite and offsite improvements.

The table below lists the exterior and interior items to be inspected and reported upon during the third inspection stage.

Exterior Inspection:

compaction of fill material

finish grading

drainage

utility connections

walks

drives

accessory buildings

retaining walls

planting

safety provisions at

- terraces

- porches

- areaways

Interior Inspection:

Page 342

design

materials, equipment, and details of their installation

interior surfaces and their finish treatment

protection against the elements and penetration of moisture

masonry pointing

caulking at openings

paint coverage

flashing

design of dwelling structure

materials and details of their installation and finish

cabinets and millwork

details and operation of systems, equipment, and fixtures related to

- plumbing

- heating

- ventilating

- electric

offsite improvements including

- utilities

- storm sewer system

- drainage channels

- grading

- curbs

- gutters

- paving

- pavement edging

- subgrade, and

- base and wearing surface and erosion control

quality and operation of hardware

quality of

- tilework

- glass

- linoleum

Page 343

- venting of attics and underfloor spaces

Individual Water Supply and Sewage Disposal System

Individual Water Supply and Sewage Disposal System

The inspector will include with the inspection report evidence obtained from the builder that installation in satisfactory to the health authority having jurisdiction.

Final Inspection

Generally, this coincides with the third inspection stage and requires the Compliance Inspection Report, VA Form 26-1839 to

include two photographs (preferably taken from the diagonally opposite front and rear corners) to record the appearance of the dwelling and indicate the grading and drainage of the site

describe the condition, suitability, and readiness for use of all equipment, fixtures and observable construction of the property

report shortcomings such as scratches in painted surfaces, poorly fitted doors, stuck windows, cracks in walls, irrespective of any arrangements made on the site for corrections, and

confirm that any instance of inferior workmanship, defective materials or equipment, or faulty installation or application of materials or equipment and/or deviation from approved plans and specifications is reported on VA Form 26-1839, and

if the property is a unit on a master appraisal either

- clearly identify any optional variation or item of equipment included in the construction, or

- state that none is included.

Special Inspections

VA may also require special inspections by the VA-assigned fee inspector at any stage of construction to help monitor cases involving

unusual site features

construction methods, or

builders with frequent construction complaints.

For cases involving major alteration or repair work, the stages at which special inspections are to be made will be determined according to the nature of the proposed work.

Re-inspection

A re-inspection is required

whenever a first- or second-stage, or special inspection shows noncompliance and the work involved will be concealed before the next regular inspection, or

as a result of noncompliance or incomplete work reported at the third-stage inspection, unless the VA field station waives the re-inspection because

Page 344

- the incomplete work is of a minor nature, and

- the lender is willing to certify that it has been satisfactorily completed.

Missed Inspections

Occasionally a required inspection may be missed through oversight by the builder or other party responsible for requesting them. To waive a missed inspection, the VA field office must be provided with

a written request signed by the lender and the veteran

evidence that the local building authority inspected the construction at the stage(s) not inspected by VA, and

Note: In areas without local inspections at prescribed construction stages, the VA inspector must provide a statement regarding his/her experience with the quality of the builder’s workmanship and the builder’s conformity with both constructions exhibits submitted to VA and VA minimum property requirements.

evidence of HUD’s consent to the waiver, if the case is HUD related.